ARTICLE · 14 APRIL 2023

Bombay High Court Clarifies The Position Regarding Payment Of Stamp Duty On Permanent Alternate Accommodation Agreements When Stamp Duty Has Already Been Paid On The Development Agreement

JSA Advocates & Solicitors
JSA Advocates & Solicitors
Contributor
JSA Advocates & Solicitors

JSA Advocates & Solicitors

Established in 1991 Our services: JSA is a leading law firm in India with more than 600...

View firm profile
Explore more from JSA Advocates & Solicitors

A division bench of the Bombay High Court ("High Court") in its recent judgment of Adityaraj Builders v. State of Maharashtra & Ors1 inter alia held that once requisite stamp duty has been paid on a development agreement entered into between a developer and co-operative housing society.

IndiaLitigation, Mediation & Arbitration

A division bench of the Bombay High Court ("High Court") in its recent judgment of Adityaraj Builders v. State of Maharashtra & Ors1 inter alia held that once requisite stamp duty has been paid on a development agreement entered into between a developer and co-operative housing society, the ancillary Permanent Alternate Accommodation Agreements ("PAAAs"), executed between the developer and the individual members of the co-operative housing society, are not liable to be separately assessed and stamped beyond the requirement under Section 4(1) of the Maharashtra Stamp Act, 1958 ("Stamp Act").

Brief Facts:

A batch of 9 (nine) Writ Petitions were filed under Article 226 of the Constitution of India before the High Court inter alia challenging the vires of two circulars dated: (i) June 23, 2015 ("2015 Circular") and (ii) March 30, 2017 ("2017 Circular") issued by the relevant stamp authorities.