Application Of ‘Doctrine Of Severability' In Terms Of Power Exercised By The Court Under Section 34 Of The Arbitration And Conciliation Act, 1996

S&A Law Offices
S&A Law Offices
Contributor
S&A Law Offices

S&A Law Offices

S&A Law Offices is a full-service law firm headquartered in Delhi NCR. The firm has 300+...

View firm profile
Explore more from S&A Law Offices

Recently, the Hon'ble Kerala High Court ("Court") in the case of M/s. Navayuga Engineering Company Limited vs. Union of India ("Navayuga Engineering") was posed with the ...

IndiaLitigation, Mediation & Arbitration

INTRODUCTION

Recently, the Hon'ble Kerala High Court (“Court”) in the case of M/s. Navayuga Engineering Company Limited vs. Union of India1 (“Navayuga Engineering”) was posed with the question ‘as to what amounts modification of award by a court?' The said question was faced by the Court in light of a recent judgment of the Hon'ble Supreme Court (“Apex Court”) in Project Director, National Highways Authority of India vs. M. Hakeem2 (“M. Hakeem”). Herein, the Apex Court has held that Section 34 of the Arbitration and Conciliation Act, 1996 (“Act”) does not contemplate modification of an award.

Therefore, the issue which was dealt in by the Court was “As to what constitutes ‘modification of an award'? Wherein if the Arbitrator has awarded separate amounts on various independent claims, then, would setting aside some of the claims, which are separable and independent of the remaining claims, constitute modification of the arbitral award?”

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from