Under Section 14 of the Insolvency and Bankruptcy Code, 2016 ("IBC"), once a company enters Corporate Insolvency Resolution Process ("CIRP"), a moratorium is declared to protect its assets and maintain it as a going concern.

IndiaInsolvency/Bankruptcy/Re-Structuring

Introduction

Under Section 14 of the Insolvency and Bankruptcy Code, 2016 ("IBC"), once a company enters Corporate Insolvency Resolution Process ("CIRP"), a moratorium is declared to protect its assets and maintain it as a going concern. However, in many redevelopment cases, defaulting developers misuse this protection. The moratorium is meant to protect the company's existing assets not to revive terminated contracts or hinder the rights of societies and landowners.

This article provides an overview of a judgement passed by the Supreme Court of India in the matter of A. A. Estates Private Limited vs. Kher Nagar Sukhsadan Co-Operative Housing Society Ltd. & Ors. wherein the Divisional Bench of the Hon'ble Apex Court comprising of Justice Pardiwala and Justice J. R. Mahadevan, while dealing with the dispute between a Society and a Developer pertaining to the termination of a Development Agreement, held that the Developer cannot be permitted protection under

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from