Introduction
In a recent decision1, the National Company Law
Appellate Tribunal, Chennai Bench (NCLAT) held
that the claims as provided in the resolution plan shall stand
frozen and will be binding on the corporate debtor and its
stakeholders, including the Central Government/State
Government/local authorities. The NCLAT held that no person will be
entitled to initiate any proceedings regarding a claim that is not
part of the resolution plan approved by an adjudicating
authority.
Facts
The NCLT, Chennai (NCLT) initiated corporate
insolvency resolution process (CIRP) against GVR
Infra Projects Limited (CD). As per the provisions
of the Insolvency and Bankruptcy Code, 2016 (IBC),
the public announcement was made by the interim resolution
professional (IRP) of the CD.