The National Company Law Tribunal, Chennai Bench vide its order dated April 25, 2022 in Mr. N. Kumar v. Tata Capital Housing Finance Ltd. held that the project-wise Corporate Insolvency Resolution Process of ...

IndiaInsolvency/Bankruptcy/Re-Structuring

The National Company Law Tribunal, Chennai Bench vide its order dated April 25, 2022 in Mr. N. Kumar v. Tata Capital Housing Finance Ltd.1 held that the project-wise Corporate Insolvency Resolution Process of a real estate company is outside the purview of the Insolvency and Bankruptcy Code, 2016 (IBC).

Brief facts of the case

Sheltrex Developers Pvt. Ltd. had launched two real estate projects namely Appur Village, Oragadam, Chennai and Nammavedu at Coimbatore. However, Corporate Insolvency Resolution Process of Sheltrex Developers Pvt. Ltd had been initiated by the National Company Law Tribunal, Chennai vide its order dated December 10, 2019. The National Company Law Tribunal, Chennai had appointed Mr. N Kumar as the Interim Resolution Professional and later he had been confirmed as the Resolution Professional. Mr. N Kumar had filed an application under Section 60(5) of the Insolvency and Bankruptcy Code, 2016 seeking permission to constitute a project-based

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from