A constitutional bench of the Supreme Court recently examined the validity of unilateral arbitrator appointment clauses in public-private contracts.

IndiaGovernment, Public Sector

A constitutional bench of the Supreme Court recently examined the validity of unilateral arbitrator appointment clauses in public-private contracts. This follows decisions TRF Ltd v Energo Engineering Projects Ltd1 and Perkins Eastman Architects DPC v HSCC India Ltd 2, which held that an ineligible person cannot appoint an arbitrator, nor can they serve as one.

The Court considered whether an arbitrator appointed from a panel curated unilaterally by a government agency is valid if the non-government party can choose two out of three arbitrators. The Court ruled such appointments are invalid.

Background

Disputes arose between the Railways and SPIC over unfulfilled contractual obligations. The Railways withheld payments, and SPIC invoked arbitration. The agreement required a three-member tribunal chosen from a panel curated by the Railways' General Manager. SPIC objected and requested the Allahabad High Court to appoint an independent arbitrator, which it did. The

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.