Under the FIDIC form, whether it is the 1999 Rainbow suite or the 1987 Fourth Edition, which is still used fairly widely in the Middle East today, obtaining a decision from either the Engineer (4th Edition) or a DAB (1999 suite) is generally a precondition to a party being entitled to commence arbitration.

GlobalReal Estate and Construction

Under the FIDIC form, whether it is the 1999 Rainbow suite or the 1987 Fourth Edition, which is still used fairly widely in the Middle East today,  obtaining a decision from either the Engineer (4th Edition) or  a DAB (1999 suite) is generally a precondition to a party being entitled to commence arbitration. This can often result in two conflicting questions:

(i) What can I do if the other party to the contract refuses to assist in the appointment of the DAB? How do I resolve my dispute if there is no Engineer and no Engineer's decision? Can I go straight to arbitration?
(ii) Do I have to go through the DAB process? The contract is at an end. Obtaining a decision of the DAB is just an unnecessary duplication of costs.