ARTICLE · 15 OCTOBER 2024

Special Limitation Period For Municipalities – Claims Must Be Issued And Served Within One Year

MLT Aikins LLP
MLT Aikins LLP
Contributor
MLT Aikins LLP

MLT Aikins LLP

FIRM OVERVIEW MLT Aikins is a full-service business law firm of more than 375 lawyers with a deep...

View firm profile
Explore more from MLT Aikins LLP

In Crooks v Rural Municipality of Marquis No. 191, 2024 SKKB 156, the Saskatchewan Court of King's Bench dismissed an action brought by a landowner against the Rural Municipality...

CanadaReal Estate and Construction

A recent decision has important implications for litigation involving Saskatchewan municipalities.

In Crooks v Rural Municipality of Marquis No. 191, 2024 SKKB 156, the Saskatchewan Court of King's Bench dismissed an action brought by a landowner against the Rural Municipality (RM) of Marquis because the plaintiff failed to serve the claim within the one-year limitation period under The Municipalities Act, SS 2005, c M-36.1, and erroneously relied on the defense of promissory estoppel. The takeaway from the Court's analysis is that parties looking to commence actions against municipalities need to be aware of the special one-year limitation period or risk dismissal.

Case summary

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from