Much has been said about Manitoba’s recent change to its basic limitation period for construction disputes, which generally reduced the time to start lawsuits from six years to two years. However, the passage of two years may not always be the end of the story for an unpaid contractor or subcontractor. In particular, where a claimant has registered a builder’s lien, the deadline to start a court proceeding to enforce that lien is connected to the lien registration date, which may extend beyond the time limit for a straightforward breach of contract claim.
In Manitoba, The Limitations Act provides that a proceeding in respect of a claim must not be commenced more than two years after the day the claim is discovered. By way of example, if a contractor issues an invoice that becomes due and is not paid, claims relating to non-payment of the invoice will be deemed discovered as of the date payment should have been received. Thus, the contractor will generally have two years from when an