ARTICLE · 26 SEPTEMBER 2022

Timing is everything: deferred commencement conditions and the Covid prescribed period under the Environmental Planning and Assessment Act 1979 (NSW)

Piper Alderman
Piper Alderman
Contributor
Piper Alderman

Piper Alderman

Helping shape the future of business in Australia with practical, commercial and cutting-edge legal...

View firm profile
Explore more from Piper Alderman

This recent case indicates that timing is everything when dealing with deferred commencement conditions for EPA consents.

AustraliaReal Estate and Construction

In the recent decision of the Land and Environment Court (LEC) in Norman v Central Coast Council [2022] NSWLEC 120 (Norman), Justice Pepper identified a drafting error in section 4.53 of the Environmental Planning and Assessment Act 1979 (NSW) (EPA Act) that creates textual inconsistencies. The decision indicates to proponents that timing is everything when dealing with deferred commencement conditions for consents.

Deferred commencement conditions of consent are commonly imposed by consent authorities pursuant to section 4.53 of the EPA Act. Deferred commencement conditions allow for project certainty and a prospective go-ahead, so long as certain requirements are satisfied in the future.