Submissions advanced and reasons given, together again! A-Civil Aust Pty Ltd v Ceerose Pty Ltd [2024] NSWCA 7

Piper Alderman
Piper Alderman
Contributor
Piper Alderman

Piper Alderman

Helping shape the future of business in Australia with practical, commercial and cutting-edge legal...

View firm profile
Explore more from Piper Alderman

Claim for retention money from termination of building contract.

AustraliaReal Estate and Construction

A recent decision of the Supreme Court, subsequently upheld by the Court of Appeal, demonstrates the need for adjudicators to keep within the bounds of the submissions to ensure that the measure of natural justice, prescribed by the Building and Construction Industry Security of Payment Act 1999 (NSW), is applied. Determination of material issues, without a party having an opportunity to be heard, puts the determination at risk.

Background

Ceerose Pty Ltd (Respondent) was the main contractor, on a site in Sydney, where A-Civil Aust Pty Ltd (Claimant) was a subcontracted to undertake excavation works. The Respondent terminated the subcontract whereupon the Claimant left the site and issued its final payment claim, which included the release of retention monies. The claim for retention of $115,577.79 was simply a line item in a schedule to the claim, without more.