Contractors on the front foot. Owner-Occupiers now exposed to Security of Payment claims.

Piper Alderman
Piper Alderman
Contributor
Piper Alderman

Piper Alderman

Helping shape the future of business in Australia with practical, commercial and cutting-edge legal...

View firm profile
Explore more from Piper Alderman

For any contracts entered into after 1st March 2021, it is Pay Now Argue Later, even in the owner occupier space.

AustraliaReal Estate and Construction

Before 1 March 2021, owner-occupiers were off-limits when it came to security of payment claims. Owner-occupier contracts were exempt from the Building and Construction Industry Security of Payment Act 1999 (NSW) (SoP Act).

Under the old rules, contractors had to commence proceedings against owner-occupiers in NCAT or a court to recover unsatisfied payment claims. It was slow, expensive and quite unhelpful in terms of cash-flow.

That has now changed for contracts entered into on and from 1 March 2021. It is now pay now argue later, even in the owner occupier space, provided the payment claim satisfies some simple requirements and is appropriately "endorsed". A great outcome for contractors.