ARTICLE · 29 SEPTEMBER 2021

Statutory Limitation Periods: A Timely Reminder Provided In Calibre Construction Corp Pty Limited V Bayside Council [2021] NSWSC 758

Parties to construction developments must be aware of the statutory limitation periods in which to bring claims.

AustraliaLitigation, Mediation & Arbitration

Summary

A recent decision in the NSW Supreme Court provides a timely reminder that parties to construction developments, including local councils, must be aware of the statutory limitation periods in which to bring claims or otherwise risk extinguishing their entitlements.

Key takeaways

It is essential to understand limitation periods (the maximum time within which a legal action can be brought) as once the right to bring a claim is lost, it is lost forever.

In NSW, the maximum period for a party to bring a claim in contract or tort is six years from the date on which the cause of action first accrued. While simple in principle, the below decision shows that calculating the relevant limitation period can be difficult, and parties should err on the side of caution when bringing claims.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from