​Race against the clock: alternative dispute resolution and limitation periods in construction disputes

Courts will try to enforce ADR clauses, even if a party might suffer detriment in terms of expiring limitation periods.

AustraliaLitigation, Mediation & Arbitration

In brief - What happens if the limitation period expires while parties engage in ADR?

Whether a contract allows for an appeal by the unsuccessful party outside underlying time limits following an alternative dispute resolution (ADR) process is a difficult question.

Parties need to comply with ADR clause even if limitation period is expiring

It is often the case that limitation periods are looming by the time:

  • damage on a project has manifested;
  • the principal has formulated its demands;
  • the head contractor (and its insurer) have settled with the principal; and
  • the head contractor's insurer is considering subrogation and recovery from contractors and third parties.