ARTICLE · 03 NOVEMBER 2008

Enforceability Of Dispute Resolution Clauses

In the recent case of Dualcorp Pty Limited v Remo Constructions Pty Limited [2008] NSWSC 749, the NSW Supreme Court confirmed that it will only enforce alternate dispute resolution clauses if it satisfied that the proposed process is complete and appropriate.

AustraliaLitigation, Mediation & Arbitration
David Jury
David Jury

In the recent case of Dualcorp Pty Limited v Remo Constructions Pty Limited [2008] NSWSC 749, the NSW Supreme Court confirmed that it will only enforce alternate dispute resolution clauses if it satisfied that the proposed process is complete and appropriate. Dualcorp Pty Ltd (Dualcorp) and Remo Constructions Pty Ltd (Remo) entered into a contract under which Dualcorp would carry out demolition, excavation and piling works for Remo at a site in Five Dock in New South Wales.

Dualcorp and Remo agreed that if disputes arose between them, they would give a notice of dispute and then submit the dispute to a dispute resolution process consisting of three stages:

  • Compulsory conferences.