ARTICLE · 23 JUNE 2024

Effect of delayed efforts in sourcing experts

The Tribunal rejected the adjournment request, citing the party's delayed efforts to retain experts.

AustraliaLitigation, Mediation & Arbitration

Recycal Pty Ltd v Director, Environment Protection Authority (No.2) [2024] TASCAT 91

In this case, the Tribunal rejected a party's adjournment request, citing its delayed efforts in retaining experts and the lack of evidence suggesting success even if allowed more time.

Background

The appellant Recycal was issued an Environment Protection Notice (EPN) by the respondent, the Director, Environment Protection Authority, under the Environmental Management and Pollution Control Act 1994 (Tas).

The appellant operates a waste storage and metal recycling facility, which functions under a planning permit with specific environmental conditions. Under the EPN, it was found that the shredder floc generated by the appellant contained contaminants classified as controlled waste.