ARTICLE · 12 MAY 2011

Court confirms that liquidated damages are an excluded amount under the Victoria

In a judgment handed down on 6 May 2011 in the case of Seabay Properties Pty Ltd v Galvin Construction Pty Ltd & Anor [2011] VSC 183 the Supreme Court of Victoria confirmed that liquidated damages are an 'excluded amount' under section 10B of the Building and Construction Industry Security of Payment Act 2002 (Vic) ("the SOP Act").

AustraliaLitigation, Mediation & Arbitration

In a judgment handed down on 6 May 2011 in the case of Seabay Properties Pty Ltd v Galvin Construction Pty Ltd & Anor [2011] VSC 183 the Supreme Court of Victoria confirmed that liquidated damages are an 'excluded amount' under section 10B of the Building and Construction Industry Security of Payment Act 2002 (Vic) ("the SOP Act").

Section 10B(1) of the SOP Act relevantly provides that excluded amounts must not be taken into account in calculating the amount of a progress payment. An 'excluded amount' is defined in section 10B(2) as, among other things:

b) "any amount (other than a claimable variation) claimed under the construction contract for compensation due to the happening of an event including any amount relating to-