ARTICLE · 04 NOVEMBER 2013

Supreme Court declares adjudication determination void in Anderson Street Banksmeadow Pty Ltd v Helcon Contracting Australia Pty Ltd

Adjudicator denies builder procedural fairness and breaches rules of natural justice.

AustraliaGovernment, Public Sector

In brief - Adjudicator denies builder procedural fairness and breaches rules of natural justice

The NSW Supreme Court has held in Anderson Street Banksmeadow Pty Ltd v Helcon Contracting Australia Pty Ltd [2013] NSWSC 491 and [2013] NSWSC 657 that an adjudication determination in favour of a piling subcontractor in the amount of $104,857.50 was void on the basis that the adjudicator denied procedural fairness to the builder in breach of the rules of natural justice.

Payment claim for piling work referred to adjudication

In the payment claim, the piling subcontractor Helcon Contracting Australia Pty Ltd ("Helcon") included claims for three variations totalling $54,000 in value (based on the variation work being 100% complete).