ARTICLE · 01 SEPTEMBER 2026

Deemed Refusal Appeals In NSW - You’re Not Out Of Time

Recent NSW planning reforms have fundamentally altered the appeal process for deemed refusals of development applications, removing the previous six-month limitation period. Understanding these changes is critical...

AustraliaFinance and Banking

A reminder to all that the Environmental planning reforms effective from 21 March 2026 (explained in more detail in our previous article), have changed the position on appeals against deemed refusals. 

The previous six-month statutory time limitation for commencing a Land and Environment Court appeal against a deemed refusal has been removed.

Section 8.10(2) of the Environmental Planning and Assessment Act 1979 now provides (emphasis added): 

8.10   Time within which appeals may be made

(2)  An appeal under this division by an applicant for development consent, or for a modification of a development consent, against a deemed refusal under section 8.11 may be made at any time—

(a)  after the expiry of the period prescribed by the regulations for the determination of the application for development consent or the modification of the development consent, and

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from