ARTICLE · 26 NOVEMBER 2025

Market Intelligence Thought Leadership Award Winner

The Latest On EPBC Clean Energy Project Approvals

Herbert Smith Freehills Kramer LLP
Herbert Smith Freehills Kramer LLP
Contributor
Herbert Smith Freehills Kramer LLP

Herbert Smith Freehills Kramer LLP

We have one of the largest Southeast Asia international law practices, working across the region...

View firm profile
Explore more from Herbert Smith Freehills Kramer LLP

Our analysis of the Environment Protection and Biodiversity Conservation Act 1999 (Cth) (EPBC Act) Public Portal has shown improvements in the timeframes for controlled action decisions...

AustraliaEnergy and Natural Resources

Our analysis of the Environment Protection and Biodiversity Conservation Act 1999 (Cth) (EPBC Act) Public Portal has shown improvements in the timeframes for controlled action decisions, for renewable energy projects located in New South Wales, Victoria and Queensland (136 days in 2023, compared to 65 days in 2025).

Despite faster referral processing times, assessment and approvals timeframes under the EPBC remain lengthy. For renewable energy projects in New South Wales, Queensland and Victoria referred since 2023, which require assessment and approval under the EPBC Act, only 1 has received a final decision.

The overview

  • 1 for 89. For the 89 renewable energy projects in NSW, Victoria or Queensland referred since 2023, which require assessment and approval under the EPBC Act, only 1 has received a final decision from the Federal Minister.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from