ARTICLE · 03 SEPTEMBER 2026

NSW Raises The Bar For IPC Referral Of Major Energy Projects, And Effectively Removes It For BESS

Herbert Smith Freehills Kramer LLP
Herbert Smith Freehills Kramer LLP
Contributor
Herbert Smith Freehills Kramer LLP

Herbert Smith Freehills Kramer LLP

We have one of the largest Southeast Asia international law practices, working across the region...

View firm profile
Explore more from Herbert Smith Freehills Kramer LLP

The NSW Government has doubled the objection threshold for electricity generating works to be referred to the Independent Planning Commission (IPC) and removed objection-based IPC referral for battery energy storage systems altogether. These changes seek to materially reduce approval risk for proponents across the energy sector.

AustraliaEnergy and Natural Resources

The NSW Government has doubled the objection threshold for electricity generating works to be referred to the Independent Planning Commission (IPC) and removed objection-based IPC referral for battery energy storage systems altogether. These changes seek to materially reduce approval risk for proponents across the energy sector.

Snapshot

The State Environmental Planning Policy (Planning Systems) Amendment (Independent Planning Commission) 2026 (NSW) (IPC Amendment) changes the IPC referral triggers so that:

  • the objection threshold trigger for electricity generating works, and mining and petroleum development is raised from 50 to 100 qualifying objections;
  • the council objection trigger is not applied for those same project classes;

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from