ARTICLE · 14 NOVEMBER 2025

NSW Clean Energy Approvals Greater Source Of Delay Than Federal EPBC, As Wind Farm Approval Costs Reach Up To $100 Million: Survey

Herbert Smith Freehills Kramer LLP
Herbert Smith Freehills Kramer LLP
Contributor
Herbert Smith Freehills Kramer LLP

Herbert Smith Freehills Kramer LLP

We have one of the largest Southeast Asia international law practices, working across the region...

View firm profile
Explore more from Herbert Smith Freehills Kramer LLP

Onshore wind energy projects, including those with battery energy storage system (BESS), face the highest average costs for obtaining State significant development...

AustraliaEnergy and Natural Resources

Onshore wind energy projects, including those with battery energy storage system (BESS), face the highest average costs1 for obtaining State significant development (SSD) consent in New South Wales (NSW) - up to $25 million, with some projects reaching up to $100 million, according to a new Herbert Smith Freehills Kramer (HSF Kramer) pulse survey.2

State significant wind and solar energy projects can take up to 12 months on average to prepare and lodge a scoping report with the NSW Department of Planning, Housing and Infrastructure (DPHI)3 to commence the formal assessment process. And, in the last five years, average approval timeframes in NSW add another 1,167 days for wind and 993 days for solar with BESS.4 Industry says total costs to secure planning approvals are higher for most clean energy projects in NSW compared to other States and Territories.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from