Tick tock, tick tock: Extension of Time claims fall foul to strict time bars!

Contractors must comply with the time provisions of the contract, even when they consider the clauses to be 'harsh'.

AustraliaCorporate/Commercial Law

The decision in CMA Assets Pty Ltd v John Holland Pty Ltd [No 6] [2015] WASC 217, has reinforced the position that contractors MUST comply with the terms of a contract – for example, time and notice provisions - otherwise they risk losing fundamental rights and claims available in the contract such as Extension of Time claims (EOT).

The case involved a subcontract between John Holland Pty Ltd (John Holland) and CMA Assets Pty Ltd (CMA). BHP contracted with John Holland to upgrade and extend a wharf at Finucane Island in Western Australia. John Holland in turn subcontracted demolition works of a shipping berth and underwater mooring and berthing dolphins to CMA.

In the course of undertaking the works CMA claimed that it was delayed by several factors such as the reinforcement of the berthing dolphins which wasn't contemplated in the subcontract, delays by John Holland in moving a shiploader and delays in giving CMA access to structures it was to demolish.