ARTICLE · 15 DECEMBER 2010

Tender documents require careful drafting: The implications of IPEX v the State of Victoria

Courts are more willing to find that a tender process contract exists where the tender documentation sets out a detailed evaluation process and states that the principal "will" or "must" follow that process.

AustraliaCorporate/Commercial Law

The importance of how to draft and respond to tender documentation has been reviewed recently in the decision of IPEX ITG Pty Ltd v State of Victoria [2010] VSC 480.

The decision raises two key issues which are particularly important for government to consider in calling for tenders and for contractors to be aware of when responding:

  • to what extent is government obliged to disclose the details of its tender evaluation process to bidders; and
  • to what extent is government obliged to comply with the tender evaluation process set out in its request for tenders?

The IPEX case also illustrates that courts are more willing to find that a tender process contract exists where a detailed evaluation process, including evaluation criteria, is set out in the tender documentation and states that the principal "will" or "must" follow that process.