ARTICLE · 23 FEBRUARY 2016

Performance management contracts: What can we learn from Portsmouth City Council v Ensign?

Contracting parties must ensure that the principal's rights under the contract's performance management regime are clear.

AustraliaCorporate/Commercial Law
Katherine Mallik
Katherine Mallik
Charlotte Gordon
Charlotte Gordon
Author LinkedIn connections

Key Points:

Contracting parties should ensure that the principal's rights under the contract's performance management regime are clear - or risk disputes as to when and how the principal can take action for service failures.

The recent UK case of Portsmouth City Council v Ensign Highways Ltd [2015] EWHC 1969 (TCC) examines how performance management regimes in outcome-based contracting arrangements should be drafted to avoid uncertainty and the risk that terms will be implied by the courts.

Background

The Portsmouth City Council was the principal to a contract for highway maintenance. Disputes between the Council and its contractor Ensign lead to the Council seeking declarations from the UK's High Court as to the operation of the contract's performance management regime.