In the recent decision of Mann
& Anor v. Paterson Constructions Pty Ltd [2019] HCA 329 on
9 October 2019, the High Court clarified the circumstances in which
a restitutionary claim on quantum meruit will be available
to a contractor who has elected to terminate the contract for the
other party's repudiation, in relation to entire contracts and
separable portion contracts.
A party repudiates a contract when it demonstrates an intention
to not carry out the contract. In response, the other party can
'accept' the repudiation and terminate the contract.
Previously, if a contract was terminated, a builder could
generally recover payment from the principal for unpaid work
performed before the contract was terminated on a quantum
meruit basis.