Get your tender in on time - but what is the time?

Tendering and procurement is becoming increasingly globalised. In this environment it is critical that owners become more sophisticated and disciplined in their approach to drafting the Request for Tender (RFT) document and more consideration needs to be given to issues that were once standard and seen to require little attention. These include the relevant time regime used for the deadline for the submission of tenders.

AustraliaCorporate/Commercial Law

Tendering and procurement is becoming increasingly globalised. In this environment it is critical that owners become more sophisticated and disciplined in their approach to drafting the Request for Tender (RFT) document and more consideration needs to be given to issues that were once standard and seen to require little attention. These include the relevant time regime used for the deadline for the submission of tenders.

The recent case of Electricity Retail Corporation t/as Synergy v Western Australia1 dealt with the issue of the time for the submission of tenders and whether or not the tender submitted by Synergy was late. The central argument focused on the time regime applicable to the closing time in the RFT. On one interpretation the tender was submitted on time while on the other the tender was late and would be excluded from evaluation.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from