Damages for breach of contract in NSW

Contractors claiming damages for wrongful termination of a contract must properly articulate and document their claim.

AustraliaCorporate/Commercial Law

In brief - Contractors claiming damages for a terminated contract must properly articulate and document their claim

The Supreme Court decision in Airloom Holdings Pty Ltd v Thales Australia Ltd [2011] NSWSC 1513 demonstrates that contractors claiming damages for wrongful termination of a contract must be clear on the sort of damages they are seeking, must have all contemporaneous documents available to support the claim and must know if GST is applicable.

Onus to establish damages is on the party claiming them

As part of establishing that damages are payable, contractors need to specify what the damages are for. This could be:

  • loss of profit
  • expenses to be recouped
  • wasted expenditure