Peter Lamont, Associate
The issue of Liquidated Damages and Penalty Clauses has been
commonly litigated and the courts are often confronted with the
question of whether the Liquidated Damages Clause is a penalty.
Surprisingly, the 1915 decision in the case of Dunlop Pneumatic
Tyre Co Ltd -v- New Garage and Motor Co Ltd still remains the
starting point for any answer to this question. The pre-eminent
principle that emerged from this case is the notion of 'genuine
pre-estimate' and the Dunlop case has stood the test of time
and remains the leading authority on this issue.
What is a genuine pre-estimate?
If forced to litigate on the issue of whether or not parties
have agreed on a reasonably accurate preestimate of loss or damage,
the key determining factor will be whether the estimate agreed upon
is regarded as liquidated damages or a penalty. It is at this point
where the parties are free to agree upon the genuine pre-estimate,
and the courts will only get