Are Liquidated Damages Really The Contractor´s Friend?

The issue of Liquidated Damages and Penalty Clauses has been commonly litigated and the courts are often confronted with the question of whether the Liquidated Damages Clause is a penalty.

AustraliaCorporate/Commercial Law

Peter Lamont, Associate

The issue of Liquidated Damages and Penalty Clauses has been commonly litigated and the courts are often confronted with the question of whether the Liquidated Damages Clause is a penalty. Surprisingly, the 1915 decision in the case of Dunlop Pneumatic Tyre Co Ltd -v- New Garage and Motor Co Ltd still remains the starting point for any answer to this question. The pre-eminent principle that emerged from this case is the notion of 'genuine pre-estimate' and the Dunlop case has stood the test of time and remains the leading authority on this issue.

What is a genuine pre-estimate?

If forced to litigate on the issue of whether or not parties have agreed on a reasonably accurate preestimate of loss or damage, the key determining factor will be whether the estimate agreed upon is regarded as liquidated damages or a penalty. It is at this point where the parties are free to agree upon the genuine pre-estimate, and the courts will only get

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from