ARTICLE · 07 AUGUST 2020

Force Majeure In The Court Of Appeal Classic Maritime Inc v Limbungan Makmur SDN [2019] EWCA Civ 1102 BHD

Quadrant Chambers
Quadrant Chambers
Contributor
Explore more from Quadrant Chambers

The first was whether a clause in a contract of affreightment protected suppliers from liability when the material to be supplied was unavailable because of a natural disaster.

United KingdomCorporate/Commercial Law

This case concerned two main issues. The first was whether a clause in a contract of affreightment protected suppliers from liability when the material to be supplied was unavailable because of a natural disaster. The second was whether, if it did not, they were in any event liable only for nominal damages because the receivers would have suffered the same loss in any event.

By a contract of affreightment, the Defendants ("Limbungan") agreed to supply cargoes of iron ore pellets to be shipped from ports in Brazil to Malaysia in tonnage to be provided by the Claimants ("Classic") in 2015 and 2016. Halfway through the shipment period, the Fundi dam burst, terminating the mining operation from which the ore was sourced. Limbungan, relying on clause 32 of the COA, disputed liability for five shipments which should have taken place subsequently, on the ground that the dam burst rendered further performance impossible. It was found that Limbungan would never have loaded the