[2021] EWHV 2207 (TCC) Judgment of the TCC 3 August 2021
Liquidated damages – contract terms interpreted
You may have read our recent eblast on the Supreme Court
judgment of
Triple Point. A decision of the TCC on this important
commercial issue has quickly followed - although on a different
aspect of liquidated damages - in the case of Eco World –
Valleymore Embassy Gardens Company Limited -v- Dobler UK Limited
(EWB -v- Dobler).
Although on the subject of liquidated damages and shortly after
the Supreme Court decision in Triple Point, the case of
EWB -v- Dobler is more focused on the interpretation of
liquidated damages clauses in construction contracts and the thorny
issue of when a liquidated damages clause may be considered to be
an unenforceable and void penalty clause.