The commentary of this article is limited to the FIDIC Red Book – The 1999 edition of the International Federation of Consulting Engineers' Conditions of Contract...

VietnamReal Estate and Construction

The commentary of this article is limited to the FIDIC Red Book – The 1999 edition of the International Federation of Consulting Engineers' Conditions of Contract for Construction for building and engineering works designed by the Employer.

In the realm of FIDIC contracts, both contractors and employers are vested with the right to lodge claims against each other. These claims can pertain to extensions of project timelines or financial compensations grounded in the contractual agreement. For employers, the procedural route for claim submission is outlined in Clause 2.5, while contractors must adhere to the directives of Clause 20.1 of the contract.

Under Clause 2.5, the Employer must notify the Contractor of any claims for payment or extension of the Defects Notification Period, providing detailed substantiation based on specific clauses. This excludes certain utility and material costs. The Engineer assesses these claims, determining any owed payment or