Considerations And New Policy Guidance Related To Extensions To The Implementation Schedule For Ballast Water Management Systems

On September 25, 2013, the U.S. Coast Guard published CG-OES Policy Letter No. 13 01 ("Policy Letter No. 13-01") providing guidance on how to submit a request for an extension of the ballast water management ("BWM") implementation schedule.

United StatesTransport

New Development

On September 25, 2013, the U.S. Coast Guard published CG-OES Policy Letter No. 13-01 ("Policy Letter No. 13-01") providing guidance on how to submit a request for an extension of the ballast water management ("BWM") implementation schedule.  For vessel owners and operators considering requesting extensions, time is of the essence as any extension requests, with certain limited exceptions, must be submitted no later than 12 months before the vessel's compliance date.  Policy Letter No. 13-01 is available at
http://www.eagle.org/eagleExternalPortalWEB/ShowProperty/BEA%20Repository/References/Regulatory/2013/USCG_BWM. 

Background

On June 21, 2012, the U.S. Coast Guard's Ballast Water Discharge Standard Final Rule ("BWM Rule") went into effect, creating new compliance requirements for U.S.-flag and foreign-flag vessels equipped with ballast tanks operating in U.S. waters.   The BWM Rule is available at http://www.gpo.gov/fdsys/pkg/FR-2012-03-23/pdf/201