ARTICLE · 23 JULY 2021

The Supreme Court Favours "Orthodox Approach" To Liquidated Damages Clauses: Triple Point Technology, Inc v PTT Public Company Ltd – Court Of Appeal Overturned

Akin
Akin
Contributor
Akin

Akin

Akin is a global law firm with more than 1,100 lawyers and advisors who pride themselves on...

View firm profile
Explore more from Akin

Sir Rupert Jackson sitting in the Court of Appeal had found that the liquidated damages clause providing for liquidated damages to be paid for each day of delay by the contractor...

United StatesReal Estate and Construction

Sir Rupert Jackson sitting in the Court of Appeal had found that the liquidated damages clause providing for liquidated damages to be paid for each day of delay by the contractor "from the due date for delivery up to the date [the employer] accepts such work" did not require liquidated damages to be paid in respect of work which had not been completed (and thus had not been accepted by the employer) before the contract was terminated. The approach taken by the Court of Appeal had raised concern. To many, it seemed odd that a contractor could miss a completion date but still avoid payment of liquidated damages simply because the contract was terminated before the obligation was fully completed. Whether the approach taken by the Court of Appeal was based on a principle of law or on the construction of the particular clause was not entirely clear. The fundamental point is now clear: the Supreme Court in Triple Point Technology, Inc v PTT Public Company Ltd [2021] UKSC 29

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from