Strict Compliance With Notice‑To‑Cure Provisions In Construction Contracts

Duane Morris LLP
Duane Morris LLP
Contributor
Explore more from Duane Morris LLP

Strict compliance with notice‑to‑cure provisions is essential in construction contracts, particularly when a contractor seeks to terminate a subcontract for cause.

United StatesReal Estate and Construction

Strict compliance with notice‑to‑cure provisions is essential in construction contracts, particularly when a contractor seeks to terminate a subcontract for cause. These provisions are designed to ensure that subcontractors receive clear, written notice of alleged defaults and a defined period to cure them before facing termination. Courts have repeatedly emphasized that failure to follow these procedures can make a termination invalid and expose the contractor to liability.

In the recent case of Pizzarotti, LLC v. MDB Development Corp., the New York Appellate Division, First Department, reinforced this principle. The general contractor terminated its concrete subcontractor on May 22, 2018, citing performance failures. The court found the termination invalid because the contractor had not complied with the subcontract's requirement that termination for cause could occur only if the subcontractor failed to cure a default within five calendar days after receiving

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

Disclaimer: This Alert has been prepared and published for informational purposes only and is not offered, nor should be construed, as legal advice. For more information, please see the firm's full disclaimer.

See more popular content from