Score One For The Contractors: The Nevada Supreme Court Declines To Subject Mechanic’s Lien Claimants To Equitable Subrogation

Fox Rothschild LLP
Fox Rothschild LLP
Contributor
Fox Rothschild LLP

Fox Rothschild LLP

Who We Are With bold growth, Fox Rothschild brings together 1,000 attorneys coast to coast. We...

View firm profile
Explore more from Fox Rothschild LLP

As anyone who follows legal matters in Nevada can attest, the fate of the partially completed Fontainebleau project is one of the most visible symbols of the economic downturn across the nation and Nevada’s construction "boom" gone "bust."

United StatesReal Estate and Construction

As anyone who follows legal matters in Nevada can attest, the fate of the partially completed Fontainebleau project is one of the most visible symbols of the economic downturn across the nation and Nevada's construction "boom" gone "bust."  Built at a cost of $2.8 billion, the Fontainebleau employed hundreds of contractors, subcontractors and materialmen and the building was (approximately) 70% complete before funds ran dry and the project was shuttered. 

In June 2009, the Fontainebleau filed for bankruptcy protection and a struggle among the property's various creditors ensued, which continues to this day.  In late 2009, financier Carl Icahn (through his entity, Icahn Nevada Gaming Acquisition, LLC) purchased the property out of bankruptcy with a successful bid of $156 million.  With the Icahn purchase, the bankruptcy estate (i.e., the debtor) realized approximately $100 million for disbursement to the project's creditors. 