Pennsylvania Court Distinguishes Between Corrective Work And Additional Work In Dismissing Mechanics’ Lien Claim

Duane Morris LLP
Duane Morris LLP
Contributor
Explore more from Duane Morris LLP

The Superior Court of Pennsylvania recently affirmed the dismissal of a contractor's mechanics’ lien on the grounds that the lien was not filed within 6 months after the completion of the work as required by Pennsylvania’s Lien Law.

United StatesReal Estate and Construction

The Superior Court of Pennsylvania recently affirmed the dismissal of a contractor's mechanics' lien on the grounds that the lien was not filed within 6 months after the completion of the work as required by Pennsylvania's Lien Law.  In Neelu Enterprises, Inc. v. Agarwal, 2012 PA Super. 276, No. 787 MDA 2012 (December 18, 2012), Agarwal, as owner, hired Neelu Enterprises, Inc., a contractor, to build a house. The contractor completed a substantial portion of the work for which it was paid. However, the owner decided to terminate the contractor before the house was completed.  The owner and contractor entered into a termination agreement on December 8, 2010. Thereafter, the contractor returned to the job site to correct deficiencies on several occasions through January 7, 2011. The contractor filed its mechanic's lien on June 23, 2011, within 6 months of January 7, 2011, but more than 6 months from the date of the termination agreement.  Pennsylvania's Lien Law provides

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from