Massachusetts Passes Law Governing Retainage On Private Contracts

Duane Morris LLP
Duane Morris LLP
Contributor
Explore more from Duane Morris LLP

A law, which governs the retainage process on private construction contracts, applies to projects of $3 million or more, entered into after November 8, 2014.

United StatesReal Estate and Construction

Massachusetts has just passed a law that governs the retainage process on private construction contracts.  It applies to projects of $3 million or more, entered into after November 8, 2014.  Essential elements are:

  • Retainage is capped at 5%.
  • The contractor must submit a notice of substantial completion within 14 days of the date substantial completion has been achieved.
  • The owner has 14 days to respond to the notice, and the project will be deemed substantially complete if the owner fails to object within that timeframe.
  • The owner is to submit a punchlist within 14 days after accepting – whether expressly or by implication – the substantial completion date.  The contractor is to pass that list along to the pertinent subs within 7 additional days. 