Itemization Of Mechanic’s Lien Not Necessary Where Construction Contract Apprised Owner Of Lienor’s Claim

Duane Morris LLP
Duane Morris LLP
Contributor
Explore more from Duane Morris LLP

New York Lien Law § 38 states that the holder of a mechanic's lien "shall, on demand in writing, deliver to the owner or contractor making such demand a statement in writing which shall set forth the items of labor and/or material and the value thereof which make up the amount for which he [or she] claims a lien, ...

United StatesReal Estate and Construction

New York Lien Law § 38 states that the holder of a mechanic's lien "shall, on demand in writing, deliver to the owner or contractor making such demand a statement in writing which shall set forth the items of labor and/or material and the value thereof which make up the amount for which he [or she] claims a lien, and which shall also set forth the terms of the contract under which such items were furnished."  In Associated Building Services Inc. v Pentecostal Faith Church,112 A.D.3d 1130, 976 N.Y.S.2d 699 (3rd Dept. 2013), the Court held that a lienor is not always required to provide an itemization of labor and materials furnished to substantiate its mechanic's lien. 

The lienor argued that it was not required to provide such a statement because the labor and materials had been furnished pursuant to a construction contract that had been performed in full.  The Appellate Court agreed.  The Court found that the statute only required the lienor to supply an