Government Claims Against Contractors And Developers Subject To Statute Of Repose Filing Deadlines, Arizona Court Of Appeals Rules

Dickinson Wright PLLC
Dickinson Wright PLLC
Contributor
Dickinson Wright PLLC

Dickinson Wright PLLC

Dickinson Wright is a full-service law firm with more than 550 lawyers, serving clients across the...

View firm profile
Explore more from Dickinson Wright PLLC

In a matter of first impression, the Arizona Court of Appeals recently ruled that government claims against contractors and developers are subject to the time limits set forth in the Construction Statute of Repose.

United StatesReal Estate and Construction

In a matter of first impression, the Arizona Court of Appeals recently ruled that government claims against contractors and developers are subject to the time limits set forth in the Construction Statute of Repose.

The Construction Statute of Repose (CSR) statute prevents contract-based claims regarding the development or construction of real property from being asserted more than eight years after substantial completion. The statute has a “safe harbor” that allows claims first discovered in the eighth year to be brought within one year after their discovery. However, in no instance may a claim be asserted more than nine years after substantial completion.

The statute covers claims for breach of contract, breach of the implied warranty, and indemnity.