What's more important: following public procurement rules,
or making sure that federal funding won't
disappear? That's the question being debated
in Sacramento, where a bid dispute has put $6.9 million in federal
funding at risk; see the article in ENR. There may be a
relatively non-controversial resolution, but the bigger question
remains – how much should a public authority be able to
exercise discretion and/or bend the rules? This
is a very slippery slope.
After a second round of bidding, the third-low bidder protested,
saying the low bidder failed to list a pertinent
subcontractor. The low bidder responded, noting
that the subcontract amount in question is below the threshold for
listing. The city, running into a federal
funding deadline, is considering suspension of the public bidding
laws (and going ahead with the low bidder, ignoring the protest) so
as not to lose out on money from the federal government.