ARTICLE · 24 JULY 2025

Florida Federal Court Makes Pivotal Ruling On Direct Vs. Consequential Damages In Design Disputes

Nelson Mullins Riley & Scarborough LLP
Nelson Mullins Riley & Scarborough LLP
Contributor
Nelson Mullins Riley & Scarborough LLP

Nelson Mullins Riley & Scarborough LLP

Nelson Mullins is a diversified law firm of more than 1,000 attorneys, policy advisors, and...

View firm profile
Explore more from Nelson Mullins Riley & Scarborough LLP

In a closely watched order issued July 11, 2025, the U.S. District Court for the Middle District of Florida addressed a previously unresolved and critical question under Florida law...

United StatesReal Estate and Construction

In a closely watched order issued July 11, 2025, the U.S. District Court for the Middle District of Florida addressed a previously unresolved and critical question under Florida law: whether remediation costs for defective design work constitute direct damages, even when the work is performed by third-party contractors. The court answered yes, denying a motion for summary judgment filed by HKS Architects Inc. and its structural engineering subcontractor, BBM Structural Engineers Inc., who argued that the Owner's multimillion-dollar structural repair claims were barred by a standard contractual waiver of consequential damages.

HKS and BBM had argued that the cost to repair the design defects were consequential damages barred by the consequential damages waiver in the agreement. The court disagreed, holding that remediation expenses incurred to correct design defects are direct damages that flow naturally and necessarily from the architect's breach of its core design