Megawatt Minute Alert: Developments On How Duke Energy Integrates Data Centers And Other New Large Load Customers In North Carolina

Nelson Mullins Riley & Scarborough LLP
Nelson Mullins Riley & Scarborough LLP
Contributor
Nelson Mullins Riley & Scarborough LLP

Nelson Mullins Riley & Scarborough LLP

Nelson Mullins is a diversified law firm of more than 1,000 attorneys, policy advisors, and...

View firm profile
Explore more from Nelson Mullins Riley & Scarborough LLP

On July 24, 2025, Duke Energy Carolinas, LLC (DEC) and Duke Energy Progress, LLC (DEP) (together, Duke) filed its response to the June 6 request by the North Carolina Utilities...

United StatesEnergy and Natural Resources

On July 24, 2025, Duke Energy Carolinas, LLC (DEC) and Duke Energy Progress, LLC (DEP) (together, Duke) filed its response to the June 6 request by the North Carolina Utilities Commission (NCUC) on how to integrate large load additions (i.e., over 100 MW) to the electric system. Interested parties may intervene and comment by August 21.

Background

Due to rapid growth in large electricity users like data centers, the NCUC now requires Duke to file semiannual reports on major electric load additions. Duke filed its first report on May 15, and a June 6 order prompted this new proceeding, requiring Duke to address several questions.

Duke's Comments

Duke's response outlines the utility's current processes, regulatory stance, and infrastructure planning strategies.