California Expands Use Of Construction Manager At-Risk To Counties On Projects Over $1 Million

Jones Day
Jones Day
Contributor
Jones Day

Jones Day

Jones Day is a global law firm with more than 2,400 lawyers in 40 offices across five continents....

View firm profile
Explore more from Jones Day

On October 3, 2013, California Governor Brown signed Senate Bill No. 328, which is now codified as Public Contract Code § 20146.

United StatesReal Estate and Construction

On October 3, 2013, California Governor Brown signed Senate Bill No. 328, which is now codified as Public Contract Code § 20146 (PCC § 20146). The new statute permits counties to utilize "construction managers at-risk" ("CMAR") in lieu of the traditional public bidding process requiring a public owner to award construction contracts to the lowest responsive, responsible bidder through the competitive bidding process. More specifically, on projects over $1 million, counties may award a CMAR contract using either the lowest responsible bidder or the best value method to a properly bonded CMAR entity.

Construction Manager at-Risk

CMAR is a relatively unusual delivery vehicle for public construction projects. The premise is that the CMAR is retained at some point shortly after the design team is assembled to assist with the design, primarily from a constructability, scheduling, and cost standpoint. Then, when the design is closer to completion (or possibly when it is