ARTICLE · 11 AUGUST 2025

Appellate Court Reaffirms Limits On Delay Damages In Construction Contracts

Duane Morris LLP
Duane Morris LLP
Contributor
Explore more from Duane Morris LLP

On June 5, 2025, the Appellate Division, First Department of the New York Supreme Court issued an opinion in Gamma USA, Inc. v. Pavarini McGovern, LLC...

United StatesReal Estate and Construction

On June 5, 2025, the Appellate Division, First Department of the New York Supreme Court issued an opinion in Gamma USA, Inc. v. Pavarini McGovern, LLC, addressing the enforceability of a no-damages-for-delay clause in a construction contract between the subcontractor and contractor. The subcontractor had brought breach of contract claims based on alleged project delays, but the court dismissed those claims, citing the clause in the subcontract that barred recovery for delay-related damages..

The court found that the subcontract's unambiguous Section 6.3 barred the subcontractor from recovering delay damages, regardless of other terms in the agreement. Section 6.3 provided:

"Notwithstanding any other provisions of this Subcontract, the Subcontractor agrees to make no claim for additional costs on account of, and assumes the risk of, any and all loss and expense for delay."

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

Disclaimer: This Alert has been prepared and published for informational purposes only and is not offered, nor should be construed, as legal advice. For more information, please see the firm's full disclaimer.

See more popular content from