The Supreme Court of Kentucky recently reaffirmed its decision
in Mattingly Bridge Co. v. Holloway & Son Const.
Co.1 which established the standard for assessing
the enforceability of a liquidated damages provision. In following
the Restatement (Second) of Contracts, the Mattingly Court
held:
Damages for breach by either party may be liquidated in the
agreement but only at an amount that is reasonable in light of the
anticipated or actual loss caused by the breach and the
difficulties of proof of loss. A term fixing unreasonably large
liquidated damages is unenforceable on grounds of public policy as
a penalty.
The Mattingly Court interpreted "anticipated
loss" to be the loss the parties estimate at the time the
contract was formed; "actual loss" refers to the damages
assessed at the time of a breach. Therefore, the Court employed a
two prong analysis under which a liquidated damages provision is
enforceable only where (1) the actual damages sustained from