On April 6, 2026, the Colorado Supreme Court held in Ralph L. Wadsworth Construction Co., LLC v. Regional Rail Partners, 2026 CO 19, that subcontractors on public projects may seek recovery of disputed or unliquidated amounts—including delay and disruption damages—in verified statements of claim under the Public Works Act. The Court also clarified that the penalty for filing an excessive claim is forfeiture of statutory remedies only, leaving common law claims available.
The Colorado Public Works Act
Because government property cannot be subjected to mechanics’ liens (the security interest contractors typically use on private projects), Colorado enacted the Public Works Act to give contractors and subcontractors analogous protections on public projects. Under section 38-26-107(1), C.R.S. (2025), a party that has furnished labor, materials, or equipment for a public project may file a “verified statement of claim”—i.e., a statutory lien—against retained contract funds held by the