ARTICLE · 22 NOVEMBER 2024

CBCA Denies The Government's Motion For Summary Judgment Based On An Issue Of Fact Regarding The Contractor's Reservation Of Rights Via A Transmission Email

Crowell & Moring LLP
Crowell & Moring LLP
Contributor
Crowell & Moring LLP

Crowell & Moring LLP

Crowell & Moring’s Doha office is a full service legal practice that serves as the firm’s regional...

View firm profile
Explore more from Crowell & Moring LLP

In Fortis Industries, Inc., CBCA 7967 (Sept. 18, 2024), the Civilian Board of Contract Appeals (CBCA) denied in part the government's motion for partial summary judgment on the issue of whether the contractor released its claims by signing a modification terminating the contract for convenience.

United StatesLitigation, Mediation & Arbitration

In Fortis Industries, Inc., CBCA 7967 (Sept. 18, 2024), the Civilian Board of Contract Appeals (CBCA) denied in part the government's motion for partial summary judgment on the issue of whether the contractor released its claims by signing a modification terminating the contract for convenience. During contract performance, the General Services Administration (GSA) imposed monthly deductions to contract payments as a response to certain performance issues. GSA later proposed to terminate the contract for convenience and sent a contract modification stating that all obligations under the contract were concluded except payment for work performed in June 2022. The contractor signed the modification but stated in its transmittal email that it was owed payment for services in May 2022 as well.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from