ARTICLE · 20 AUGUST 2025

A Sigh Of Relief For Public Agencies: Existing Permit Conditions Such As Traffic Impact Mitigation Fees, Imposed On Classes Of Development, Can Satisfy The Nollan/Dolan Test

Kronick Moskovitz Tiedemann & Girard
Explore more from Kronick Moskovitz Tiedemann & Girard

On July 29, 2025, on remand from the United States Supreme Court, the Court of Appeal in Sheetz v. County of El Dorado held that (1) the Takings Clause does not prohibit permit conditions...

United StatesLitigation, Mediation & Arbitration

On July 29, 2025, on remand from the United States Supreme Court, the Court of Appeal in Sheetz v. County of El Dorado held that (1) the Takings Clause does not prohibit permit conditions, such as impact fees, based on schedules or formulas assessing an entire class of development rather than a specific development; and (2) that El Dorado County's legislatively imposed permit condition, a traffic impact mitigation ("TIM") fee, withstood the Nollan/Dolan requirements of essential nexus and rough proportionality. In doing so, the Court held that a permit condition imposed on a class of development must be tailored and supported with the same degree of specificity as a permit condition that targets a particular development. Thus, while permit conditions for classes of development are permissible and can satisfy Nollan/Dolan, this case serves as an important reminder that public agencies should have ample evidence when adopting land-use permit conditions.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from